Starting today, Monday March 30th 2020, construction crews will begin mobilizing in the north hill area to prepare for work. Milling of the existing surface will start on Thursday and is expected to last 2-3 days. Once Milling is complete, patching will take place for 2-4 weeks, which will be followed by 1-2 months of paving.